Waldo Broadband Corporation

Member Towns

Freedom, Liberty, Montville, Palermo and Searsmont

Work Continues throughout the summer.

Click here for Signup details

The Waldo Broadband Corporation (WBC) partnership grant between the Maine Connectivity Authority and Direct Communications was approved in June 2024. The contractual completion date is October 15, 2026.

WBC residents who sign up during this time period (before 10/15/26) will have the $100 installation waived.

All inquiries about the status of the build, installation schedule and services should be directed to Direct Communication.‍ ‍‍ ‍

WBC will continue to act in an advisory role during the build phase. WBC will also, in its non-profit role, promote opportunities for community education and additional grants to serve the community needs once the network is completed.

Project Summary and Status as of June 2026

● Grant Awarded December 2023 - $10,867,737

  • Total Financial Commitment (Direct Communications)- $4,517,000

  • Total Cost of Project - $15,384,737

● Contract Negotiations (Completed)

● Permitting/Make Ready - (Completed)

  • Pole Surveys (7211 poles) (Completed)

● Pre-orders (Ongoing)

● Construction Planning and Steps (Complete)

  • Design (Complete)

  • Field Surveys (Complete)

  • Engineering (Complete)

  • Permitting (Complete)

Construction Phases (Ongoing)

1. Mainline Cable Installation (Near Completion)

2. Mainline Splicing (In Progress)

3. Mainline Roads to Secondary Roads

  1. Cabinet Installation & Splicing (In Progress)

  2. Secondary Road Splicing (In Progress)

4. Pole to Home Cable Run (Drop Wire)(In Progress/ Completed in many areas)

5. Homeside Splicing (In Progress/ Completed in many areas)

6. Scheduling Installs (In Progress/ Completed in many areas)

  • ONT Installation & Service Activation (In Progress/ Completed in many areas)

Check out our FAQs page for lots of good information.