
Waldo Broadband Corporation
The Waldo Broadband Corporation contract agreement between the Maine Connectivity Authority and Direct Communications was approved on June 2024. The contractual completion date is October 15, 2026.
Check out our FAQs page for lots of good information.
Project Summary and Status as of March 2025
● Grant Awarded December 2023 - $10,867,737
Total Financial Commitment (Direct Communications)- $4,517,000
Total Cost of Project - $15,384,737
● Contract Negotiations (Completed)
● Permitting/Make Ready - (Completed)
Pole Surveys (7211 poles) (Completed)
● Pre-orders (Ongoing)
● Construction Planning and Steps (Near Completion)
Design (Complete)
Field Surveys (Complete)
Engineering (Design Near Completion)
Permitting (98% Completion)
Construction Phases (Ongoing)
1. Mainline Cable Installation (May/2025)
2. Mainline Splicing (May/2025)
3. Mainline Roads to Secondary Roads
Cabinet Installation & Splicing
Secondary Road Splicing
4. Pole to Home Cable Run (Drop Wire)
5. Homeside Splicing
6. Scheduling Installs
ONT Installation & Service Activation